Electrical Energy Auditing and Enhanchment of Power System at Basbari Water Treatment Plant, Kathmandu

Authors

  • Dipesh Dhakal Department of Mechanical and Aerospace Engineering, Pulchowk Campus, Institute of Engineering, Tribhuvan University, Nepal
  • Nawraj Bhattarai Department of Mechanical and Aerospace Engineering, Pulchowk Campus, Institute of Engineering, Tribhuvan University, Nepal
  • Navin Kumar Jha Department of Mechanical and Aerospace Engineering, Pulchowk Campus, Institute of Engineering, Tribhuvan University, Nepal

DOI:

https://doi.org/10.3126/jacem.v9i1.71442

Keywords:

Energy Consumption, Maximum Demand, Specific Energy Consumption, Energy Audit, Energy

Abstract

The water treatment plant (WTP) employs a variety of electrical machines and utilities, making it an intensive energy consumption plant. In this study, an energy audit was conducted on the Basbari WTP in Kathmandu, Nepal to identify the hotspots that consume most of the energy in the plant and recommend solutions for energy-efficient operation. A power quality analyzer was used to analyze the energy consumption patterns of electrical parameters and the TOD meter load survey data is taken from the electricity authority. The study found that transmission pumps and backwash/makeup pumps consume 77% and 6% of the energy, respectively. Efficient utilization of pump motors could result in an annual cost savings of NRS 109,681.12 from transmission pumps, backwash pumps, and make pumps. The payback period for light replacement and installation of a capacitor bank is 2.16 years and 1.95 years, respectively.

Downloads

Download data is not yet available.
Abstract
15
PDF
5

Downloads

Published

2024-11-14

How to Cite

Dhakal, D., Bhattarai, N., & Jha, N. K. (2024). Electrical Energy Auditing and Enhanchment of Power System at Basbari Water Treatment Plant, Kathmandu. Journal of Advanced College of Engineering and Management, 9(1), 137–151. https://doi.org/10.3126/jacem.v9i1.71442

Issue

Section

Articles